Building Update - 9/13/2026
What happened this week:
Coming up this week:
- Dirt work and grading completed
- Paint is 93.7% complete
- AV work initiated
- Lighting fixtures delivered
- Electrical, Plumbing, and Riser Room progressing
Coming up this week:
- HVAC installs
- flooring arrives
- potentially tiling the bathrooms